PAK LAW GPT — Pakistan Case Law AI justice scale emblemPAK LAW GPTCase law · Urdu & English

ISLAMIC REPUBLIC OF PAKISTAN through Secretary, Ministry of Defence vs RASHID BUILDERS (PVT — 2024 SCMR 1816 SUPREME-COURT

Case information

Citation
2024 SCMR 1816 SUPREME-COURT
Court
Supreme Court of Pakistan
Year
2024
Reporter
SCMR
Parties
ISLAMIC REPUBLIC OF PAKISTAN through Secretary, Ministry of Defence vs RASHID BUILDERS (PVT
Subject matter
Criminal
Provisions referred to
S. 10---S

Fields are extracted from the reported citation and judgment text. Where a detail is not stated in the record, it is not shown.

Judgment text as reported

ISLAMIC REPUBLIC OF PAKISTAN through Secretary, Ministry of Defence VS RASHID BUILDERS (PVT.) LIMITED S. 10---Suit for recovery of money---Contractual liabilities---"But-for" Test---Applicability---Delay caused in completion of project---Determination---Concurrent findings of facts by two Courts below---Misreading and non-reading of evidence---Respondent/plaintiff filed suit for recovery of money along with costs for delay caused in completion of contract due to fault on the part of appellant/authorities---Judgment and decree passed by Trial Court was maintained by High Court---Validity---Nature of delays meant that respondent/plaintiff was eligible for multiple extensions of time, and appellants/authorities granted such extensions---Inclement weather was beyond the control of appellants/authorities and respondent/plaintiff was allowed extension of time---When extensions of time were granted and the project was completed then question was why respondent/plaintiff initiated recovery proceedings---Such recovery proceedings were nothing but an effort to avoid paying the refund that appellants/authorities were rightfully owed by respondent/plaintiff---"But-for" Test, was to ask if delays by respondent/plaintiff were independent of the delays by appellants/ authorities---If delays of respondent/plaintiff were only happening because appellants/authorities had caused delays first, then the delays of appellants/authorities were the root cause---If respondent/defendant had also been causing delays regardless of the actions of appellants/ authorities, then the delays of respondent/plaintiff were independent---Applying the "But-For" Testmeant that the delays of respondent/ plaintiff were independent and he was not entitled to recover amount through the suit---Supreme Court set aside conclusions arrived at by High Court as well as Trial Court which were patently improbable and perverse----Supreme Court dismissed the suit filed by respondent/ plaintiff and set aside the judgments and decrees passed by two Courts below---Appeal was allowed.

Other judgments reported in 2024 SCMR

Back to the case-law library · Search Pakistani case law in Urdu or English